This month's reasons for slow progress are:
(1) "the worst October weather on record"
(2) the lorry drivers strike - so no supplies
(3) the economy - our window fitters are really struggling with cash flow
(4) feast days and holidays
We had to spend our first day sweeping water out of our flooded roof space which was leaking into the sitting room. The rain had been coming down the chimney and through some broken tiles. Marc fitted an Ikea bag over the chimney but we're still waiting for the tiles to be repaired.
And there has been quite significant progress.
Our ballustrades are now finished.



.
The windows and shutters are almost finished. The glass door in the photo on the right is the extra door we had put in so that we could see our favourite view. You can see the same door in the photo on the left with the blue roller shutter pulled down. (Also, note Ikea bag on chimney - carefully chosen to match the shutter colour)